The Story
Back in 1992, I was working for a consulting company named The Kernel Group (TKG). During this time, I was put in charge of porting
I looked at the code with a coworker of mine, and he came to the conclusion that if
As a result, evil upper management drastically expanded the project bid to $325,000, and my coworker and I thought that this was a ridiculously high price. We believed that we were gouging the customer and that they would never accept it.
Yet they did accept it, and once the project began, we proceeded to discover how truly terrible we as software engineers were at the task of project estimation. To make a long story short, the porting schedule expanded to exceed our original estimate and we consumed not only all of the $325,000, but a whole lot more on top of it.
The Formula
Now our consulting company was religious about tracking employee time on a per-project basis, and so we broke every project into phases: requirements/specification, design, coding, testing, debugging, documentation, training, etc. This project was no different in that respect; we broke it down into its respective phases as well.
Just before we started working on the project in question, I read a book called Practical Software Metrics for Project Management and Process Improvement by Robert B. Grady. (By the way, this is a truly fabulous book that I would highly recommend to anyone who is managing software development projects.) According to the book, one of Grady’s rules of thumb is that 6-8% of every software project is usually eaten up in the requirements/specification phase.
One of the conclusions that Grady comes to in his work is that you can use this fact to estimate total project size. In other words, if it took 60 hours to do the specification, that's probably 6% of the job and the job will be 1000 hours. Following such logic, a six hour specification implies a 100 hour job. Since the specification always comes first in any project, you can get some pretty reliable estimates from this method alone. In fact, in my experience as both a programmer and the CEO of a software company, I have found it to be incredibly accurate and useful.
A second way to triangulate this project estimate is to ask experts in the area for their opinions – hopefully they will be better at project estimation than my coworker and I were that first time. A third way is to select an appropriate metric for estimation. For example, one could use line of code counts or function points in estimating the length and scope of software projects. For architecture projects, you might use number of pages in the drawings or square feet planned as similar analogies. Every project has some gross measure of its size that is available at the outset and can be used to plan the overall project in addition to this method I’ve described of tracking time against the earliest phases.
So back to the story. We really blew it on estimating and bidding on that first project for
Partially due to the strength of the solution and how well it ran on IBM’s AIX operating system,
For a consultancy that is doing fixed-cost projects, this concept of using the standard ratio of requirements phase to overall project length is a very powerful project estimation technique. It can eliminate erroneous bidding and its resulting costs, which is a major concern for such companies.
Accurate Bidding
Overbidding on a consulting job means that you won't get the work in the first place, because the potential customer will give it to your competitor at a cheaper price. Underbidding, however, means you will win the deal and lose money. Neither situation is acceptable for businesses today, and yet most consultancies do a poor job in this area. One way to make more precise bids is to use a key performance indicator, which is a tool used to measure progress towards a strategic business goal. For example, the number you want to minimize in this situation is defined by the formula [(E-A)/E], where:
E = estimated hours to complete the project
A = actual hours spent to complete the project
It is important to keep this KPI value as close to zero as possible, which indicates that you are bidding on projects more accurately.
Just tracking this number is a great first step towards better bidding, and you can get the necessary data to calculate it from any timesheet system, including a paper one. Automated timesheet systems, however, are generally even more effective in this area because they often have reports to calculate the KPI figure for you.
Improving adherence to your estimate can be difficult for some companies until they understand the ratio concept described above. An example of this is illustrated in the following diagram, which shows how the formula can work for any business. Your company’s magic number may not be 6-8% like Grady’s, but once you determine your own ratio for specification to total project length, you can use it again and again.
Making it Work
I currently run a software company, Journyx, and I can assure you that this project estimation technique continues to be successfully employed by many of our customers to their great advantage. It is easy to implement and you can do it too. Once you do, you will start producing laser sharp estimates before you know it. And that’s a result we can all feel good about requiring.
Happy estimating!