You are here: Home Blogs Seven Key Areas to Create a Bullet-Proof Project Status Report
Sunday, 12 February 2017 21:38

Seven Key Areas to Create a Bullet-Proof Project Status Report

Written by 
Rate this item
(0 votes)
This content is from the Method123 weekly email dated 2017.09.02

Seven Key Areas to Create a Bullet-Proof
Project Status Report


Status reporting is the minimum communication element for a project manager. The primary purpose is to manage stakeholder expectations. The project Status Report summarizes the progress of the project to date, and provides a list of the critical changes, risks and issues which require their attention.

If you want to create a bullet-proof status report, then make sure that your report includes each of the following sections:

Executive Summary

Summarize the overall progress and any key achievements since the last update. State whether the project is currently on schedule and within budget.

Schedule

Describe the overall schedule status in terms of green (on track), yellow (at risk) or red (need to re-baseline), If the schedule is yellow, state what you are doing to get back to green. If the schedule is red, describe how you will re-baseline scope, schedule and/or budget to get back in synch. Also list any actual and estimated deliverable completion date variances. 

Costs

Describe the overall cost status in terms of green (on track), yellow (at risk) or red (need to re-baseline). If the cost is yellow, state what you are doing to get back to green. If the costs is red, describe how you will re-baseline scope, schedule and/or budget to get back in synch. Also list any actual and budgeted expenditure variances.

Scope

Describe the overall scope status in terms of green (on track), yellow (at risk) or red (need to re-baseline). If the scope is yellow, state what you are doing to get back to green. If the costs is red, describe how you will re-baseline scope, schedule and/or budget to get back in synch.

Quality

Describe the overall quality status in terms of green (on track), yellow (at risk) or red (need to re-baseline). If the quality is yellow, state what you are doing to get back to green. If the costs is red, describe how you will change the project to meet quality expectations. This is normally changing project processes to meet existing quality expectations, although sometimes the quality criteria need to change to become more realistic.

Risks

Risks are potential problems that may arise in the future. Your project should have an updated risk register. You should pull out any interesting or critical risks to provide visibility to management stakeholders - along with how you are responding to the risk.

Issues

Issues are large, current problems that are impacting your project. Issues are big enough that all of them should be listed for stakeholder review. For each issue, describe your plan to address and sold the problem.

...
That's it. If you create a project report which describes each of the sections above, you will keep your project stakeholders better informed of the overall progress of the project, and manage their expectations about the state of the project. Remember, if your stakeholders are surprised, you likely have not done a good job of managing expectations. 

At TenStep we are dedicated to helping organizations achieve their goals and strategies through the successful execution of critical business projects. We provide training, consulting and products for organizations to help them set up an environment where projects are successful. This includes help with strategic planning, portfolio management, program / project management, Project Management Offices (PMOs) and project lifecycles. For more information, visit www.TenStep.com or contact us at This email address is being protected from spambots. You need JavaScript enabled to view it.
Read 722 times
Login to post comments

News and Promotions

Keep up to date with the latest happenings by signing up for our newsletter. Subscribe below.

Twitter Update

Who's Online

We have 841 guests and no members online

Got something to say?